Wikipedia defines Suburban Sprawl thus: “Urban sprawl or suburban sprawl describes the expansion of human populations away from central urban areas into low-density, monofunctional and usually car-dependent communities, in a process called suburbanization.” While Culver isn’t exactly racing down the road to strip malls, it’s worth looking at the changes occuring in recent and proposed developments in Culver.
Culver’s early development was very traditional. Despite dealing with the curvature of Lake Maxinkuckee, a traditional grid system was used for both the commercial and residential areas with the section of Lake Shore Drive along the Park being one of the few deviations with some curvature to reflect the lake shore. Since that time, the newer subdivisions have not followed the grid. The Riggings, Maple Ridge and Edgewood Estates are all dead end or loop streets with no plans to tie into the grid. It’s a little cheesy, but Adam Conover of “Adam Explains Everything” does a quick run down of some of the issues here:
We had the preconstruction meeting for the Damore Amphitheater this morning. We had all the staking completed and the tiers painted on the grass… but the paint didn’t show up too well through the snow! (See Right) Happy April!!! Not exactly the way we wanted to start the project…
The timelike on this calls for completion by Memorial Day. Despite the snow fall Mother Nature so rudely dropped on us today, we should still be good to go for that. There may be some plantings that stretch that date if the nurseries can’t open, but it’s too soon to be pessimistic about that. We have most of our orders placed and should be good to go with all of the hardscape.
FH Decks and Landscaping, Inc. will be our major subcontractor on this project, completing the earthwork, stone work and landscape installation. We wanted to keep this project local and were happy that it turned out that way.
This project was part of Culver’s Stellar Communities application in 2016, but through fundraising and other grants, Culver was able to move forward on this project without Stellar. This was done through IHCDA’s Patronicity program. That made room for other project funding in the 2017 Stellar application. Thanks go to the Damore family stepping up as the lead sponsor. Their leadership was invaluable.
We made the paper this week with our Sand Hill Farm Apartment’s project appearing in the Culver Citizen. Beth Pare and her son came out in the rain for a walk-thru this past Tuesday. Despite the rain there was still a lot of activity at the site. Drywall was being delivered as we spoke.
There’s not much doubt that the follow-thru on our Stellar 2016 application pledge of completing workforce housing helped us secure Stellar Community designation in 2017. Preliminary site work had already begun when the Stellar Site Visit occurred. Our successful Stellar designation makes this phase I of workforce housing. Our application for IHCDA funding goes in this July. We will be starting with a market study shortly and will plan for that construction in 2019.
Progress has been good this week. All but four windows are in place. Those four have been left out on the second floor until the rest of the drywall is delivered. The drywall will be place on the second floor through those openings using a boom truck. The majority of the exterior doors have been installed. The shingles are on. The interior winding stairs to the second floor bedrooms have been installed. And progress continues on Plumbing and Electrical rough-in.
Last week we had meetings with Elkay to discuss the cabinetry that they are providing. They made an additional change to include Elkay sinks in each unit. Thank you Elkay!
As we all know, this winter has been challenging to say the least. Four 50+ degree swings so far this year. Despite that we’ve muddled along and made some progress at the Sand Hill Farm site. Most of the work has been underground, but as of last Friday, wall panels have begun to stand up on the building pad. We;re now in 3D! The erection crew worked over the weekend and about half the first floor is framed. At this rate they will make quick work of things and we’ll be weathered in before we know it.
In the picture you can see that the first three panels at the Southwest corner are in place. The panels are 2×6 framing with OSB exterior sheathing. The 2×6 framing allows for additional insulation. The 2×6 studs are on 24″ centers to reduce the areas of heat transfer for energy efficiency. California Corners (Green That Saves Green 101) were used to increase insulation as well. The window and door openings are pre-framed, so once the panels are up and the house wrap is installed, the fenestrations (our big word of the day) will be filled quickly too.
Note the fire hydrant in the lower right of the picture. The main water lines are in place as well. We have a fire hydrant waiting on the Town to bring water to it. My understanding is that the street and utilities project should go out for bid within 2 weeks with bids due in around 6 weeks. We’ll be needing that soon! They’ve promised installation by the 1st of June.
The building will be sprinkled, so we already have the riser in place in the maintenance room for fire protection. Rough-in for that will begin once framing is complete so we can get things placed prior to drywall installation.
It’s great to see things coming together after some of the earlier struggles.
We received a very cool Christmas Card (right) from our friends at SRKM Architecture. They used an elevation from Sand Hill Farm apartments as their cover picture adding a couple of wreaths on the door. A great idea to memorialize the project this way! We really appreciate their efforts and can’t wait to see if the building looks as good in person as it does in pictures. Thanks guys! Merry Christmas!
Sand Hill Farm Apartments are moving along. Footing and frost walls have been poured. We’re taking advantage of this week’s warm spell to get the perimeter insulation in place and complete the backfill. Installation of interior underslab infrastructure will begin Thursday. We hope to be pouring slabs next week. Things are moving forward!