We made the paper this week with our Sand Hill Farm Apartment’s project appearing in the Culver Citizen. Beth Pare and her son came out in the rain for a walk-thru this past Tuesday. Despite the rain there was still a lot of activity at the site. Drywall was being delivered as we spoke.
There’s not much doubt that the follow-thru on our Stellar 2016 application pledge of completing workforce housing helped us secure Stellar Community designation in 2017. Preliminary site work had already begun when the Stellar Site Visit occurred. Our successful Stellar designation makes this phase I of workforce housing. Our application for IHCDA funding goes in this July. We will be starting with a market study shortly and will plan for that construction in 2019.
Progress has been good this week. All but four windows are in place. Those four have been left out on the second floor until the rest of the drywall is delivered. The drywall will be place on the second floor through those openings using a boom truck. The majority of the exterior doors have been installed. The shingles are on. The interior winding stairs to the second floor bedrooms have been installed. And progress continues on Plumbing and Electrical rough-in.
Last week we had meetings with Elkay to discuss the cabinetry that they are providing. They made an additional change to include Elkay sinks in each unit. Thank you Elkay!
Second Floor Exterior Walls going up at the southeast corner of the building
A lot has happened in the last week on the Sand Hill Farm Apartment project. The first floor walls of the apartments have been placed, the second floor deck is nearly complete and they have started the installation of second floor walls. It’s great to see some blue skies today. That will make a big difference in moving things forward.
With all the wet conditions in Marshall County, we’re glad we chose the site we did. “Sand Hill” is not just a catchy moniker, it’s descriptive for the site. Part of the hill was sacrificed for backfill and it’s provided a base that has drained well in this wet period. That’s not to say our hearts don’t go out to those hurt by Mother Nature this past week. We hope everyone remains safe and the appropriate steps can be taken to prevent the stormwater events of the past week from being repeated.
As we all know, this winter has been challenging to say the least. Four 50+ degree swings so far this year. Despite that we’ve muddled along and made some progress at the Sand Hill Farm site. Most of the work has been underground, but as of last Friday, wall panels have begun to stand up on the building pad. We;re now in 3D! The erection crew worked over the weekend and about half the first floor is framed. At this rate they will make quick work of things and we’ll be weathered in before we know it.
In the picture you can see that the first three panels at the Southwest corner are in place. The panels are 2×6 framing with OSB exterior sheathing. The 2×6 framing allows for additional insulation. The 2×6 studs are on 24″ centers to reduce the areas of heat transfer for energy efficiency. California Corners (Green That Saves Green 101) were used to increase insulation as well. The window and door openings are pre-framed, so once the panels are up and the house wrap is installed, the fenestrations (our big word of the day) will be filled quickly too.
Note the fire hydrant in the lower right of the picture. The main water lines are in place as well. We have a fire hydrant waiting on the Town to bring water to it. My understanding is that the street and utilities project should go out for bid within 2 weeks with bids due in around 6 weeks. We’ll be needing that soon! They’ve promised installation by the 1st of June.
The building will be sprinkled, so we already have the riser in place in the maintenance room for fire protection. Rough-in for that will begin once framing is complete so we can get things placed prior to drywall installation.
It’s great to see things coming together after some of the earlier struggles.
Our friends at SRKM Architecture shared a picture with us from the past. We think the project was Robin Hood Leisure Living at Grace Village in Winona Lake. That’s our best guess anyway (per John Singleton). Pictured are Larry Berger and P.T. McKinnis. (Check out that mullet!)
Robin Hood Homes are one and two bedroom duplexes in a condominium setting. They are part of the Grace Village Retirement Community. It is a staged community with several retirement living options.
This was the first project where we put radiant heating into the floor. It was a learning experience… particularly working with the residents to teach them the lag involved with this type of heat. Residents that were used to the instant gratification of forced air heat were often over-adjusting the thermostats. Until they got the hang of it, they struggled with temperature swings due to readjusting the thermostat before it had reached temperature and vice versa when they turned it down.
Thanks SRKM for the picture!
From Left to Right, Bob Porter – Culver Utilities Superintendent, Jack Jordan – State Representative, Dale Cramer – Lake City Bank, Joel Samuelson – Culver Town Council, Kevin Berger – Easterday Construction Co., Inc., Tammy Shaffer – Culver Town Council, Ginny Munroe – Culver Town Council President.
I was pretty impressed with the turn out for the Sand Hill Farm Ground Breaking Ceremony last Tuesday, November 5th. There were around 35 people there including representatives from the Town, County and State. Town Council President – Ginny Munroe, County Commissioner – Kevin Overmyer and Lake City Bank Representative – Dale Cramer all spoke in support of the project. I truly appreciated the kudos. We broke out the gold shovels and made a showing of it for the Press.
Speaking about Workforce Housing at the Stellarbration on November 5th. From Left to Right, Kevin Berger – Easterday Construction Co., Inc., Brian Meek – Elkay Wood Products, Karen Shuman – Culver Community School Corp., Don Fox – Culver Academies
The theme from everyone was how this was a first step towards addressing Culver and Marshall County’s workforce housing needs. Currently, Marshall County has an unemployment rate of less than 3%. The general “rule” is that once it gets below 4%, everyone that wants to work is working. Since there are still jobs going unfilled, the next step would be to recruit labor from outside the County. That’s difficult when there isn’t housing available for those new workers. Sand Hill Farm hopes to be a first step towards addressing this. This is Easterday Construction being a community partner/leader.
Along with the several of our area newspapers, we received coverage from the three major networks, ABC 57, WNDU 16 and WSBT 22. See WSBT links for video clips of the Stellerbration event and ABC 57 and WNDU 16 for a little more about the Sand Hill Farm ground breaking. They were all kind with their video editing and made us look good!
Housing was the signature piece of Culver’s Stellar Communities application and I truly think we wouldn’t have scored as highly without the Phase I portion of this project underway. It showed that even without winning Stellar designation last year, Culver moved forward, addressing the needs identified in our Strategic Investment Plan. Having Regional Cities also put money towards this project was positive too. It showed a regional commitment that the State values. At several of the presentations, I was pleased to stand with Culver’s three largest employers, Elkay Wood Products, Culver Community School Corporation and Culver Academies, as their representatives spoke about the needs this project was addressing and how this needs to be just the start.
Tuesday was a true ground breaking as we made our presentations with an excavator working in the background. Currently the building pad is nearly complete and the excavator should be cutting in footings in the next week. the site looks quite different.
We’re racing the weather to get the slab done so we can work through the winter. Since it is slab-on-grade construction, that means a fair amount of underground utility work needs to be completed as well. Cross your fingers for us!
It sounds like the Town will delay their street work until Spring. That shouldn’t affect us as long as they are complete sometime in June. The goal is to be open next summer before the new school year starts. That would meet many of our goals, i.e. increased Town population, increased school enrollment and an expanded labor pool.
+++++++++++++++++++++++++++++++++++++++
Thanks to Nancy Tyree at MCEDC for the pictures.