As we all know, this winter has been challenging to say the least. Four 50+ degree swings so far this year. Despite that we’ve muddled along and made some progress at the Sand Hill Farm site. Most of the work has been underground, but as of last Friday, wall panels have begun to stand up on the building pad. We;re now in 3D! The erection crew worked over the weekend and about half the first floor is framed. At this rate they will make quick work of things and we’ll be weathered in before we know it.
In the picture you can see that the first three panels at the Southwest corner are in place. The panels are 2×6 framing with OSB exterior sheathing. The 2×6 framing allows for additional insulation. The 2×6 studs are on 24″ centers to reduce the areas of heat transfer for energy efficiency. California Corners (Green That Saves Green 101) were used to increase insulation as well. The window and door openings are pre-framed, so once the panels are up and the house wrap is installed, the fenestrations (our big word of the day) will be filled quickly too.
Note the fire hydrant in the lower right of the picture. The main water lines are in place as well. We have a fire hydrant waiting on the Town to bring water to it. My understanding is that the street and utilities project should go out for bid within 2 weeks with bids due in around 6 weeks. We’ll be needing that soon! They’ve promised installation by the 1st of June.
The building will be sprinkled, so we already have the riser in place in the maintenance room for fire protection. Rough-in for that will begin once framing is complete so we can get things placed prior to drywall installation.
It’s great to see things coming together after some of the earlier struggles.
It’s always been kind of a joke that I don’t know how old Easterday Construction is. I tell people that Great Grandpa (Russell) Easterday was too busy running a new business to worry about commemorating business milestones. I’m sure, like all small business owners, at that point he was just concerned about keeping it in the black. He wasn’t thinking about any kind of legacy. We’ve done a little better with that regarding Becky’s new business, Berger Audiology. Chances are it won’t be here 85 years from now, but I’m sure that’s what Russell thought too!
Dad used to tell me he thought the company began in the 30’s, but on a walk to lunch I happened to notice the concrete marker on the Elementary School Gym named us as the contractor when the “Community Building” as it was known then, was dedicated in 1929. (Hard to read, but I’ve included a picture below.) That moved the date back to at least 1928. So the History Corner in the Culver Citizen last week qualifies as a Blast from the Past project. I’m assuming that this was one of the first large projects completed by Easterday Construction, though I can’t say for certain. Our current office is across the Slate Street to the west, but at that time the property was still part of Russell’s farm and was only used as staging for equipment and supplies. The current office wasn’t built until the 50’s (again history is sketchy), while in the beginning the offices were on the second floor of the State Exchange Bank Building (currently First Farmers Bank & Trust).
Dedication Marker on the south side of the Culver Elementary School Gym
Easterday Construction has been involved in several additions and renovations at the Culver Community Schools over the years, so there s a lot of history there. Dad played high school basketball there. (He still blames getting thrown into one of those block walls just off the court for his reoccurring back problems.) When I was in school, that was the Jr. High School Gym. I had gym class there and played (briefly) on the Jr. High basketball team before acknowledging that growth spurt didn’t translate into talent.
It’s always interesting when ties to the past like this come up. It usually results in conversations with those with memories of those times. Unfortunately those of that generation are getting fewer and fewer.
I used the new Sand Hill Farm Logo today in a post to Town, Gown and Lake about the Habitat for Humanity site at Sand Hill Farm. (If you’re not on Town, Gown and Lake and and want to read that post, I’ve included it below.) I chose to work with Shelly Schrimsher of Unlocked Creativity since this is a local project. I’d seen her work through her assistance to the Town on the Stellar projects and the new Town Logo. She helped me work through some of the ideas I already had and I think the collaboration resulted in something versatile that I can use for years.
I wanted to include a graphic that brought the sand hill and associated woods into the logo. She did this in a creative way bringing the curve of the hill slope into the “s” in sand. I also asked for the graphic to be independent of the words to make it more versatile and she was able to to do that. And finally I had a vision of the entry sign made from rusted, cut, multi-layer metal on a gabion base/background to carry through the Culver Charrette field stone theme. From several examples I showed her, she was able to provide a mock-up capturing the concept. Now I can show the fabricators what the goal is – which makes it more likely they’ll achieve it for me. This is out for quotes now.
Overall this was a good experience and I am pleased with the results. You’ll be seeing the logo show up more and more as the project moves forward. Give Shelly a shot if you have similar needs.
Image from Habitat for Humanity of Marshall County website
I have always had a plan to include a Habitat for Humanity site at Sand Hill Farm. I recently met with representatives of Habitat for Humanity of Marshall County and the Town of Culver to discuss this. They were excited about the opportunity and were happy to provide additional information.
If you’re interested in possibly participating in a Habitat Home at Sand Hill Farm, I encourage you to look at the information on their site and fill out an application. Copies of the application can be found on their website here and can be picked up at the Town Hall in Culver. The plan would be to offer a home in late 2018 or sometime in 2019. Once accepted, an applicant must put in 100 hours of service before the build starts, so the sooner you start the process, the better.
Habitat for Humanity is always looking for volunteers, so if you would like to volunteer you can check out those opportunities on their website here. If you would like to contribute, they accept donations directly at: 116 South Walnut Street, Plymouth, IN and for convenience, you can also contribute to them through Marshall County Community Foundation where they have an established fund. The Community Foundation site accepts credit card donations.
To the right is an article that appeared in The Pilot News, December 18, 2017 discussing the impact of the Regional Cities Initiative. The study was conducted by Ball State University and concluded that it is making a noticeable difference in attracting talented young workers to the area.
Marshall County is part of the North Central Region along with St. Joseph and Elkhart Counties. Most of the funds for our region have been allocated and in Marshall County we’re seeing the impact through assistance in worker housing, manufacturing centers, expanded Boys & Girls Club facilities and an Aquatic Center. In Culver alone, the initiative has helped the Town provide infrastructure to Sand Hill Farm for entry-level housing and money has been set aside for assistance with an E-Commerce center which may provide entrepreneurial opportunities and worker training space. (Culver was in line for additional RCI grants, but the 60% private equity requirement proved daunting for a small community to achieve.)
It’s important to recognize what our local organizations have done to achieve these goals. Marshall County would not have had this opportunity without the foresight of the Marshall County Community Foundation (MCCF) and their initial investment of $10k into the program. That seed money was what put us on the map for this and made the initial connections to St. Joseph and Elkhart Counties. If Linda Yoder hadn’t taking this to the MCCF board and sold it, it wouldn’t have happened.
The hand-off from there went to Marshall County Economic Development Corporation (MCEDC). Without their efforts, many of the projects submitted by Marshall County would not have made the list before the application was submitted. Then the follow up to keep the dollars allocated to Marshall County stayed with Marshall County largely came down to the shepherding of Jerry Chavez and MCEDC. They were able to get a reallocation of funds to housing initiatives when original projects fell through and then when one of the four housing projects didn’t come to fruition, they were able to secure the money towards the other projects that were viable.
The money that went to the housing project in Culver helped Culver achieve Stellar Community designation this year. It’s a domino effect and currently the dominos are falling in our direction. This was former Governor Mike Pence’s vision when he spearheaded this program. Inject funds into regions that demonstrate the desire and determination to move forward and great things can happen. Let’s hope this continues to buoy our region, county and communities creating the excitement and drive to move us forward.