The framing for this project is all panelized. There is enough duplication between the apartment units that there are multiple walls of the same size that can be constructed more economically as panels in a factory setting. The exterior walls arrive with the exterior sheathing installed. Window and door openings are located and framed as part of these panels at the factory. We have subcontracted with a framing crew to install the wall panels, trusses and roof sheathing. The first of the wall panels arrived today and are ready to be placed. The framing crew will be here tomorrow morning to start installation. By this time next week the building will have taken shape!