Culver Garden Court Update

Main Corridor with Drywall Installation Underway

It’s been a while since my last update on Culver Garden Court.  Things are proceeding quickly. 

Rough-in is complete on wiring for the electrical, security and fire alarm systems.  Plumbing rough-in is complete.  HVAC rough-in is nearly complete.  This has allowed installation of the wall insulation.  Exterior wall insulation is complete and sound batts have been installed where required between units.  Drywall installation has begun.  The first thing to be drywalled will be the ceilings.  This will allow blown-in insulation to be installed in the attic.

On the exterior, the faux stone wainscot installation has begun.  Most of the stone is in place.  Next will be wall caps and the column bases.  Once wall caps are in place, siding and soffit installation will begin. 

Sidewalk Construction Underway

Installation of concrete walks and curbs is currently underway.  This will allow us to proceed with paving preparations.  We made some decisions on revised locations for the sign and flag pole, so the installation of those items can proceed as well.

 

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Copyright 2011 - Easterday Construction Company, Inc. - All rights reserved.
top